The contract includes an allowance for decorative lighting, and the owner selects fixtures above the allowance. What should be administered?

Correct Answer

D) Reconcile the allowance

A201 allowance provisions govern how selections and costs affect the Contract Sum.

Answer Options
A
Bid security forfeiture because selections changed
B
Automatic deletion of the lighting scope
C
Final payment without comparing actual cost
D
Reconcile the allowance

Why This Is the Correct Answer

A201 allowance provisions govern how selections and costs affect the Contract Sum.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.