A subcontractor seeks final payment before required closeout items are submitted. Which AIA A401 area controls?

Correct Answer

D) Closeout pay condition

A401 includes subcontract progress-payment and final-payment requirements.

Answer Options
A
A701 bidder representations
B
A201 owner financing evidence
C
A201 owner stop-work right
D
Closeout pay condition

Why This Is the Correct Answer

A401 includes subcontract progress-payment and final-payment requirements.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.