The initial decision process does not resolve the claim. What AIA A201 process commonly precedes binding dispute resolution?

Correct Answer

D) Mediation

A201 commonly requires mediation before binding dispute resolution.

Answer Options
A
Rebidding
B
Permit closeout
C
Bid modification
D
Mediation

Why This Is the Correct Answer

A201 commonly requires mediation before binding dispute resolution.

Why the Other Options Are Wrong

Option A: Rebidding

Rebidding skips the written authority, scope, price, notice, or release control needed for the contract control.

Option B: Permit closeout

Permit closeout skips the written authority, scope, price, notice, or release control needed for the contract control.

Option C: Bid modification

Bid modification skips the written authority, scope, price, notice, or release control needed for the contract control.

Memory Technique

Contract square for Owner Continue: scope, authority, price, paper.

Reference Hint

Open-book path: tab AIA A201-2017 to Article 15 Section 15.3 Mediation; match the role, instrument, notice point, and timing before selecting.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.