The owner may accept a minor nonconforming finish with an agreed credit. Which AIA A201 topic is relevant?

Correct Answer

A) Owner-approved variance

A201 addresses acceptance of nonconforming Work and appropriate adjustment.

Answer Options
A
Owner-approved variance
B
Automatic bid withdrawal
C
Survey requirement
D
Subcontract payment timing

Why This Is the Correct Answer

A201 addresses acceptance of nonconforming Work and appropriate adjustment.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.