EstatePass
Contract AdminContractsmedium40% of exam part

The current change directive is not available in the field office. Which AIA A201 duty was missed?

Correct Answer

C) Maintain site documents and records

A201 requires the Contractor to keep contract documents, changes, and related records at the site.

Answer Options
A
Store only prebid quotes after award
B
Send current drawings only to the surety
C
Maintain site documents and records
D
Use a supplier invoice as the drawing record

Why This Is the Correct Answer

A201 requires the Contractor to keep contract documents, changes, and related records at the site.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.