A superintendent says subcontractors can coordinate themselves without contractor oversight. Which AIA A201 duty responds?

Correct Answer

B) Contractor supervision of the Work

A201 requires the Contractor to supervise and direct the Work.

Answer Options
A
Architect supervision of every trade employee
B
Contractor supervision of the Work
C
Building official control of the contractor's labor plan
D
Owner lender management of daily field crews

Why This Is the Correct Answer

A201 requires the Contractor to supervise and direct the Work.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.