A serious unsafe condition is observed and the Owner directs affected work to stop. Which AIA A201 right is involved?

Correct Answer

D) Suspension authority for unsafe conditions

A201 contains an Owner right to stop the Work under stated conditions.

Answer Options
A
Owner right to modify sealed bids after opening
B
Supplier right to certify payment to the contractor
C
Subcontractor right to waive OSHA requirements
D
Suspension authority for unsafe conditions

Why This Is the Correct Answer

A201 contains an Owner right to stop the Work under stated conditions.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.