An owner-approved prime contract change adds work to a subcontractor's scope. What AIA A401 process should the GC administer?

Correct Answer

C) A corresponding subcontract change

A401 includes processes for changes in the Subcontract Work corresponding to contract changes.

Answer Options
A
A free field directive with no subcontract record
B
A bid withdrawal because the scope changed after award
C
A corresponding subcontract change
D
A final lien waiver before pricing the change

Why This Is the Correct Answer

A401 includes processes for changes in the Subcontract Work corresponding to contract changes.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.