A bidder receives an addendum changing door hardware before the bid due date. Under AIA A701, what should the bidder do?
Correct Answer
A) Incorporate and acknowledge the addendum as required
A701 governs addenda as part of the bidding documents and bid submission process.
Why This Is the Correct Answer
A701 governs addenda as part of the bidding documents and bid submission process.
Why the Other Options Are Wrong
Option B: Save the addendum for final payment review after construction
Save the addendum for final payment review after construction skips the written authority, scope, price, notice, or release control needed for addenda.
Option C: Treat it as a minor change issued by the architect after award
Treat it as a minor change issued by the architect after award skips the written authority, scope, price, notice, or release control needed for addenda.
Option D: Ignore it unless the preferred subcontractor also acknowledges it
Ignore it unless the preferred subcontractor also acknowledges it skips the written authority, scope, price, notice, or release control needed for addenda.
Memory Technique
Addenda square for Closes Sealed: scope, authority, price, paper.
Reference Hint
Open-book path: tab AIA A701-2018 to Bidding Documents; Addenda; compare the role, timing, and required instrument in the stem.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?