Contract AdminContractsmedium40% of exam part

The owner wants to occupy one completed floor while the rest of the project continues. Which AIA A201 subject should be reviewed?

Correct Answer

D) Partial occupancy or use

A201 addresses partial occupancy or use of a portion of the Work before final completion.

Answer Options
A
Bid modification before opening
B
Subcontractor bid listing
C
Owner evidence of financing before procurement
D
Partial occupancy or use

Why This Is the Correct Answer

A201 addresses partial occupancy or use of a portion of the Work before final completion.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.