Contract AdminContractsmedium40% of exam part

The architect issues a written order clarifying trim alignment with no price or time effect. Which AIA A201 category fits?

Correct Answer

D) A Minor Change in the Work

A201 allows minor changes ordered by the Architect when they do not affect Contract Sum or Contract Time.

Answer Options
A
A termination for convenience
B
A bid-security claim
C
A final completion certificate
D
A Minor Change in the Work

Why This Is the Correct Answer

A201 allows minor changes ordered by the Architect when they do not affect Contract Sum or Contract Time.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.