The owner and contractor agree on scope, price, and time for added millwork. Which AIA A201 instrument fits?

Correct Answer

B) A Change Order signed through the contract process

A Change Order is used when the parties agree on a change in the Work and its contract impacts.

Answer Options
A
A bid addendum sent after the contract is executed
B
A Change Order signed through the contract process
C
A daily report note with no agreement on time or money
D
A certificate of substantial completion for unfinished work

Why This Is the Correct Answer

A Change Order is used when the parties agree on a change in the Work and its contract impacts.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.