The architect returns a submittal marked reviewed. The installer says this shifts installation errors to the architect. Which AIA A201 principle applies?

Correct Answer

D) Architect review does not relieve contractor submittal and installation responsibility

A201 limits the effect of submittal review and preserves contractor responsibilities.

Answer Options
A
Architect review converts the submittal into a change order automatically
B
Owner occupancy waives every later installation defect, while bypassing the contract path for claims and disputes
C
The supplier becomes the contract administrator after review, without separating design review from means-and-methods control
D
Architect review does not relieve contractor submittal and installation responsibility

Why This Is the Correct Answer

A201 limits the effect of submittal review and preserves contractor responsibilities.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.