Contract AdminContractsmedium40% of exam part

After award, the owner asks for the planned sequence and milestone dates for the contractor's work. Which AIA A201 submittal is involved?

Correct Answer

A) Contractor's construction schedule

A201 requires the Contractor to prepare and submit a construction schedule.

Answer Options
A
Contractor's construction schedule
B
Certificate of final payment, and omitting the affected party from the required communication
C
Bid modification form, and treating an unresolved claim as automatically approved
D
Notice of commencement form

Why This Is the Correct Answer

A201 requires the Contractor to prepare and submit a construction schedule.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.