The contract carries a hardware allowance and the owner later selects a more expensive lockset package. What should the GC administer?

Correct Answer

C) Allowance accounting and any required Contract Sum adjustment

A201 allowance provisions govern how allowance selections and cost differences affect the Contract Sum.

Answer Options
A
A bid-security demand because allowances are pre-award only
B
Automatic deletion of the hardware scope from the contract
C
Allowance accounting and any required Contract Sum adjustment
D
Final payment release without comparing selected cost to allowance

Why This Is the Correct Answer

A201 allowance provisions govern how allowance selections and cost differences affect the Contract Sum.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.