A subcontractor offers non-specified fasteners that are cheaper but do not meet the listed corrosion requirement. Which AIA A201 duty controls?
Correct Answer
C) Provide materials required for proper execution of the Work
A201 requires the Contractor to furnish labor, materials, equipment, and services required for the Work.
Why This Is the Correct Answer
A201 requires the Contractor to furnish labor, materials, equipment, and services required for the Work.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner wants one contractor representative to receive jobsite communications and coordinate daily field work. Which AIA A201 role fits?
Next Question
A project addendum revises the door hardware specification two days before bid. What should the estimator do before submitting the bid?