The owner sees a safety hazard and wants work stopped immediately at the affected area. Which AIA A201 owner right may be involved?

Correct Answer

D) Owner's right to stop the Work

A201 includes an Owner right to stop the Work under stated circumstances.

Answer Options
A
Owner's right to issue every shop drawing correction directly to suppliers
B
Bidder's right to modify a sealed bid after opening, without matching the response to the correct AIA article
C
Subcontractor's right to certify the prime contractor's payment
D
Owner's right to stop the Work

Why This Is the Correct Answer

A201 includes an Owner right to stop the Work under stated circumstances.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.