A Florida bidder receives an addendum changing the specifications before bid day. Under AIA A701, how should it be handled?

Correct Answer

A) Incorporate and acknowledge the addendum as part of the bidding documents

A701 addresses addenda as part of the bidding documents.

Answer Options
A
Incorporate and acknowledge the addendum as part of the bidding documents
B
Ignore it because addenda apply only after final completion, and let the permit reviewer resolve the private contract issue
C
Treat it as a monthly payment application for installed work, and use that shortcut to decide the addendum requirement, while moving the dispute into the bid archive only
D
Use it only if a subcontractor voluntarily changes its quote

Why This Is the Correct Answer

A701 addresses addenda as part of the bidding documents.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.