The Work is stopped for a prolonged period for reasons described in the contract, and the contractor is evaluating whether it may terminate. Which AIA A201 article should be reviewed?

Correct Answer

A) Termination by the Contractor provisions

A201 Article 14 includes provisions for termination by the Contractor.

Answer Options
A
Termination by the Contractor provisions
B
Bid security forfeiture before award, and use that shortcut to decide the termination by contractor requirement, while using the schedule update as the contract change
C
Shop drawing review for general conformance
D
Schedule of values allocation for payment review

Why This Is the Correct Answer

A201 Article 14 includes provisions for termination by the Contractor.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.