The architect learns the GC has not paid a subcontractor and lien exposure may exist. What AIA A201 payment concept may apply?

Correct Answer

D) Withholding certification as necessary to protect the Owner from loss

A201 lists grounds for withholding certification to protect the Owner.

Answer Options
A
Automatic final payment because subcontractor payment is never considered
B
Bid withdrawal before award as the only remedy for nonpayment
C
Transfer of payment certification to the unpaid subcontractor
D
Withholding certification as necessary to protect the Owner from loss

Why This Is the Correct Answer

A201 lists grounds for withholding certification to protect the Owner.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.