EstatePass
Contract AdminContractsmedium40% of exam part

The owner asks why each pay application must be tied to a cost breakdown. Which AIA A201 document provides that basis?

Correct Answer

A) The schedule of values used as the basis for applications for payment

A201 uses the schedule of values as the basis for reviewing applications for payment.

Answer Options
A
The schedule of values used as the basis for applications for payment
B
The bid tabulation used only to compare bidders before award
C
The shop drawing log used only to list submittal dates, and treat owner occupancy as acceptance of the procedure
D
The notice to proceed used only to authorize the start of Work

Why This Is the Correct Answer

A201 uses the schedule of values as the basis for reviewing applications for payment.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.