An owner-directed phasing change affects the critical path. What must the GC generally use to request more time under AIA A201?

Correct Answer

D) The contract claim or change process for an extension of Contract Time

A201 handles extensions of time through contract delay, change, and claim procedures.

Answer Options
A
An automatic extension with no notice because the owner caused the issue
B
A revised bid form after final payment has been requested, and use that shortcut to decide the change time requirement, and treat the project meeting agenda as the contract instrument
C
A supplier certification that substantial completion has occurred
D
The contract claim or change process for an extension of Contract Time

Why This Is the Correct Answer

A201 handles extensions of time through contract delay, change, and claim procedures.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.