The agreement says the Work must reach Substantial Completion by a stated date. Which AIA A201 article defines and administers that timing concept?

Correct Answer

C) Article 8 provisions for Contract Time, progress, and completion

A201 Article 8 addresses Contract Time, progress, and completion.

Answer Options
A
AIA A701 bid security provisions used before contract award, and use that shortcut to decide the article completion requirement, without matching the remedy to the cited AIA article
B
AIA A401 subcontract payment provisions used only for trade invoices
C
Article 8 provisions for Contract Time, progress, and completion
D
Article 3 cleanup provisions used only for jobsite rubbish

Why This Is the Correct Answer

A201 Article 8 addresses Contract Time, progress, and completion.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.