The architect issues a written clarification that does not affect price or time. Which AIA A201 change category fits?

Correct Answer

B) A Minor Change in the Work ordered by the Architect

A201 allows the Architect to order minor changes that do not affect Contract Sum or Contract Time.

Answer Options
A
A final payment application closing all unresolved claims, and use that shortcut to decide the architect change requirement, and use trade sequencing to decide a payment entitlement
B
A Minor Change in the Work ordered by the Architect
C
A bid-security demand after the low bidder is selected
D
A termination notice issued without contract cause

Why This Is the Correct Answer

A201 allows the Architect to order minor changes that do not affect Contract Sum or Contract Time.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.