Contract AdminContractsmedium40% of exam part

The owner and GC agree to add a canopy, increase the Contract Sum, and extend Contract Time. Which AIA A201 instrument records the agreement?

Correct Answer

D) A Change Order agreed by the owner and contractor and otherwise processed under the Contract Documents

A Change Order records agreed changes in Work, Contract Sum, or Contract Time.

Answer Options
A
A field report that only records site weather and manpower, and use that shortcut to decide the change order requirement, and treat the subcontract invoice as the architect's decision
B
A bidder qualification statement submitted after award, without preserving the owner's review step in the file
C
A final certificate for payment before the canopy is priced
D
A Change Order agreed by the owner and contractor and otherwise processed under the Contract Documents

Why This Is the Correct Answer

A Change Order records agreed changes in Work, Contract Sum, or Contract Time.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.