The contract includes a signage allowance because final selections are not complete. How should the GC administer it?

Correct Answer

D) Track allowance cost and adjust the Contract Sum as the contract requires

A201 allowance provisions govern cost accounting and Contract Sum adjustment.

Answer Options
A
Treat the allowance as free work that never affects the Contract Sum
B
Use the allowance only as bid security before contract award, and close the issue in the estimator's pricing notes
C
Convert the unused allowance automatically into contractor profit
D
Track allowance cost and adjust the Contract Sum as the contract requires

Why This Is the Correct Answer

A201 allowance provisions govern cost accounting and Contract Sum adjustment.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.