Contract AdminContractsmedium40% of exam part

The architect rejects nonconforming work before substantial completion. Under AIA A201, what must the contractor generally do?

Correct Answer

A) Correct rejected Work that fails to conform to the Contract Documents

A201 requires correction of Work rejected or failing to conform to the Contract Documents.

Answer Options
A
Correct rejected Work that fails to conform to the Contract Documents
B
Wait until final payment before addressing any rejected Work
C
Ask the low bidder to decide whether correction is necessary
D
Treat the architect's rejection of nonconforming work as a bidding addendum

Why This Is the Correct Answer

A201 requires correction of Work rejected or failing to conform to the Contract Documents.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.