A trade proposes an unapproved lower-cost door closer after the substitution deadline. What should the GC do?

Correct Answer

A) Follow substitution requirements

Substitution requests must follow the required timing and approval procedure.

Answer Options
A
Follow substitution requirements
B
Use the closer and disclose it after inspection
C
Treat the supplier quote as design approval
D
Put the decision in the first pay application

Why This Is the Correct Answer

Substitution requests must follow the required timing and approval procedure.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.