The architect rejects a portion of installed wall protection. What should the PM do?

Correct Answer

D) Track nonconformance correction

Nonconforming work requires tracking through correction and verification.

Answer Options
A
Remove the rejection from the record
B
Wait until warranty expiration
C
Treat it as bid withdrawal
D
Track nonconformance correction

Why This Is the Correct Answer

Nonconforming work requires tracking through correction and verification.

Why the Other Options Are Wrong

Option A: Remove the rejection from the record

Remove the rejection from the record belongs to a different file or record trail; it does not prove the nonconformance event.

Option B: Wait until warranty expiration

Wait until warranty expiration belongs to a different file or record trail; it does not prove the nonconformance event.

Option C: Treat it as bid withdrawal

Treat it as bid withdrawal belongs to a different file or record trail; it does not prove the nonconformance event.

Memory Technique

Administrative proof for Medical Office: event, approval, receipt, follow-up.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Quality control; nonconforming work and corrective action; verify quantity math, FL permit status, notice step, or field-control timing.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.