The project has been inactive for months and is restarting. What should the PM confirm?
Correct Answer
D) Confirm permit status
Permit status and extensions must be verified with the authority having jurisdiction.
Why This Is the Correct Answer
Permit status and extensions must be verified with the authority having jurisdiction.
Why the Other Options Are Wrong
Option A: Original bid spread
Original bid spread does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for permit expiration.
Option B: Furniture sequence
Furniture sequence does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for permit expiration.
Option C: Last supplier quote
Last supplier quote does not satisfy the required party, deadline, proof, license, bond, insurance, or agency trigger for permit expiration.
Memory Technique
Good work cannot rewind a missed extensions trigger in Restarts Pause.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1 Section 105 permits and local administration; verify quantity math, FL permit status, notice step, or field-control timing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?