A low waterproofing quote excludes flood testing required by the specifications. What should the estimator do before carrying it?

Correct Answer

A) Clarify the scope gap before carrying the quote

Bid leveling requires complete comparable scope before a proposal is carried.

Answer Options
A
Clarify the scope gap before carrying the quote
B
Carry the low quote unchanged and wait for leaks
C
Move testing to the owner's furniture vendor
D
Treat the exclusion as accepted because the quote is low

Why This Is the Correct Answer

Bid leveling requires complete comparable scope before a proposal is carried.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.