A change estimate has $36,800 direct cost and an allowed 18% markup. What total should be submitted?
Correct Answer
A) $43,424
Apply markup to direct cost.
Why This Is the Correct Answer
Apply markup to direct cost.
Why the Other Options Are Wrong
Option B: $39,744
$39,744 is below the supported result for markup; it likely uses the wrong base, period, or account bucket.
Option C: $42,320
$42,320 is below the supported result for markup; it likely uses the wrong base, period, or account bucket.
Option D: $45,264
$45,264 is above the supported result for markup; it likely adds an unsupported amount or compares the wrong financial base.
Memory Technique
Markup fence: markup starts at cost, margin looks back from price.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Change estimating; markup on direct cost; verify quantity math, FL permit status, notice step, or field-control timing.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?