EstatePass
Contract AdminPreconstructionmedium27% of exam part

A takeoff includes 2,400 lf of #4 rebar. If #4 bar weighs 0.668 lb per lf and 5% waste is carried, what weight should be estimated?

Correct Answer

C) 1,684 lb

Multiply length by unit weight and add waste.

Answer Options
A
1,603 lb
B
1,764 lb
C
1,684 lb
D
2,004 lb

Why This Is the Correct Answer

Multiply length by unit weight and add waste.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.