The permit reviewer returns egress comments requiring revised drawings. What is the correct response?
Correct Answer
C) Respond through permit review
Plan review comments must be resolved through permit review and revised documents.
Why This Is the Correct Answer
Plan review comments must be resolved through permit review and revised documents.
Why the Other Options Are Wrong
Option A: Start affected work from rejected sheets
Start affected work from rejected sheets may relate to another site control, but it does not remove or guard the plan review comments exposure being tested.
Option B: Have a supplier answer code comments alone
Have a supplier answer code comments alone may relate to another site control, but it does not remove or guard the plan review comments exposure being tested.
Option D: File comments in closeout and ignore them
File comments in closeout and ignore them may relate to another site control, but it does not remove or guard the plan review comments exposure being tested.
Memory Technique
If Retail Receives can still reach the worker, the control is decoration.
Reference Hint
Open-book path: tab Florida Building Code, Building, 8th Edition (2023), Chapter 1 Administration to Chapter 1 Sections 105 and 107 permit review and documents; verify the quantity, Florida notice/permit rule, or field-control record before answering.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?