A direct contract exceeds the notice threshold and the first inspection is scheduled. What must be in the permit record when required?

Correct Answer

A) Provide recorded notice information

Chapter 713 links notice-of-commencement documentation to building permit inspections.

Answer Options
A
Provide recorded notice information
B
Final lien waiver from every supplier before rough inspection
C
Subcontract bid tab from preconstruction
D
Owner punch-list email after occupancy

Why This Is the Correct Answer

Chapter 713 links notice-of-commencement documentation to building permit inspections.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.