A reflected ceiling plan conflicts with the lighting schedule before bid. What should the bidder do?

Correct Answer

B) Submit the required prebid clarification

Prebid conflicts should be resolved through the required question and addendum process.

Answer Options
A
Choose the cheaper interpretation and keep the conflict out of the record
B
Submit the required prebid clarification
C
Ask the lighting supplier to issue the official design interpretation
D
Wait until final payment to decide which fixture count controls

Why This Is the Correct Answer

Prebid conflicts should be resolved through the required question and addendum process.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.