A bid unit price line includes 520 lf of sawcutting at $7.80 per lf plus $675 layout charge. What amount should be carried?

Correct Answer

C) $4,731

Extend lineal quantity and add layout charge.

Answer Options
A
$4,056
B
$4,576
C
$4,731
D
$5,251

Why This Is the Correct Answer

Extend lineal quantity and add layout charge.

Why the Other Options Are Wrong

Option A: $4,056

$4,056 is below the supported result for unit price line; it likely omits allowance, conversion, coverage, or final round-up.

Option B: $4,576

$4,576 is below the supported result for unit price line; it likely omits allowance, conversion, coverage, or final round-up.

Option D: $5,251

$5,251 is above the supported result for unit price line; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Measure to extend, adjust for lineal, then let Site Bid set the finish line.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Estimating unit-price work; lineal unit extension; verify the quantity, Florida notice/permit rule, or field-control record before answering.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.