A slab is 84 ft by 62 ft and 6 in thick. Including 5% waste, how many cubic yards of concrete should be carried?

Correct Answer

A) 101.3 cy

Convert thickness to feet, compute cubic feet, convert to cubic yards, and add waste.

Answer Options
A
101.3 cy
B
96.4 cy
C
106.0 cy
D
121.5 cy

Why This Is the Correct Answer

Convert thickness to feet, compute cubic feet, convert to cubic yards, and add waste.

Why the Other Options Are Wrong

Option B: 96.4 cy

96.4 cy is below the supported result for slab concrete; it likely omits allowance, conversion, coverage, or final round-up.

Option C: 106.0 cy

106.0 cy is above the supported result for slab concrete; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Option D: 121.5 cy

121.5 cy is above the supported result for slab concrete; it likely double-counts allowance, uses the wrong unit, or rounds too early.

Memory Technique

Estimator Checks takeoff: count the condition before counting the package Tie the cue to Slab Concrete Estimator Checks.

Reference Hint

Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Estimating and quantity takeoff; slab volume and waste; verify the quantity, Florida notice/permit rule, or field-control record before answering.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.