Contract AdminPermitsmedium20% of exam part

The jurisdiction requires online inspection requests by 2 p.m. for next-day inspections. What should the GC do?

Correct Answer

B) Follow the local administrative scheduling procedure

Local administrative rules can govern inspection scheduling under the permit workflow.

Answer Options
A
Call the lowest bidder and ask it to schedule the inspection
B
Follow the local administrative scheduling procedure
C
Wait until final payment to ask whether scheduling mattered
D
Use the subcontractor quote as the inspection request

Why This Is the Correct Answer

Local administrative rules can govern inspection scheduling under the permit workflow.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.