A field change affects an egress door swing shown on approved permit drawings. What should happen before installing the change?

Correct Answer

C) Route the revision through the required approval process

FBC administration requires work to follow approved documents or approved revisions.

Answer Options
A
Install the change and mention it only in the final invoice
B
Use the subcontractor sketch as the approved permit drawing
C
Route the revision through the required approval process
D
Ask the furniture vendor to approve the egress path

Why This Is the Correct Answer

FBC administration requires work to follow approved documents or approved revisions.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.