Contract AdminPermitsmedium20% of exam part

The tenant asks to start electrical rough-in while the permit application is still under review. What should the GC verify first?

Correct Answer

B) Required permit issuance before regulated work

FBC Chapter 1 requires permits for regulated work unless an exception applies.

Answer Options
A
Whether the electrician's invoice has a cost code
B
Required permit issuance before regulated work
C
Whether the bid bond premium has been paid
D
Whether the furniture vendor has reserved delivery

Why This Is the Correct Answer

FBC Chapter 1 requires permits for regulated work unless an exception applies.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.