Contract AdminPermitsmedium20% of exam part

A direct contract over the threshold is ready for first inspection, but no recorded notice information is in the permit file. What should be done?

Correct Answer

A) Provide the required notice of commencement copy or recording information

Chapter 713 links required notice-of-commencement documentation to building permit inspections.

Answer Options
A
Provide the required notice of commencement copy or recording information
B
Ask the inspector to use the bid recap as the notice
C
Wait until final payment to record project information
D
Use the subcontractor's first invoice as the owner's recorded notice

Why This Is the Correct Answer

Chapter 713 links required notice-of-commencement documentation to building permit inspections.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.