A major elevator quote expires before the owner's planned award date. What is the best preconstruction response?

Correct Answer

A) Address quote validity or carry escalation risk before bid submission

Quote validity affects the reliability of a bid or proposal.

Answer Options
A
Address quote validity or carry escalation risk before bid submission
B
Assume the expired quote remains binding without vendor confirmation
C
Use the bid bond as the elevator vendor's price guarantee
D
Move the elevator cost to warranty because award is delayed

Why This Is the Correct Answer

Quote validity affects the reliability of a bid or proposal.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.