A parking patch is 18,500 sf at 2 in compacted thickness. Using 110 lb per square yard per inch, how many tons of asphalt are required?
Correct Answer
C) 226 tons
Convert square feet to square yards, apply pounds per inch, then convert to tons.
Why This Is the Correct Answer
Convert square feet to square yards, apply pounds per inch, then convert to tons.
Why the Other Options Are Wrong
Option A: 113 tons
113 tons is below the supported result for asphalt tonnage; it likely omits allowance, conversion, coverage, or final round-up.
Option B: 206 tons
206 tons is below the supported result for asphalt tonnage; it likely omits allowance, conversion, coverage, or final round-up.
Option D: 452 tons
452 tons is above the supported result for asphalt tonnage; it likely double-counts allowance, uses the wrong unit, or rounds too early.
Memory Technique
Retail Includes takeoff: count the condition before counting the package.
Reference Hint
Open-book path: tab Principles and Practices of Commercial Construction, 11th Edition, 2024 to Sitework estimating; asphalt tonnage; verify the quantity, approval point, notice rule, or field record before answering.
More Contract Admin Questions
An owner assumes the architect's site visit means the architect is supervising the contractor's crews. What AIA A201 concept corrects that assumption?
The GC and owner disagree about what a specification requires. Under AIA A201, who commonly provides interpretations and decisions during administration?
The architect observes work that does not conform to the Contract Documents. Which AIA A201 architect authority may apply?
A subcontractor says the prime contract general conditions do not apply to its work. Under AIA A401, what should the GC point to?
An addendum adds 18 access panels at $315 each installed. What amount should be added to the bid?
A slab-on-grade is 96 ft by 54 ft and 5 in thick. Including 7% waste, how many cubic yards of concrete should be carried?
An addendum adds 14 doors at $685 each installed. What additive amount should be added to the bid for those doors?
A CMU wall area is 2,240 sf after openings. If one block covers 1.125 sf and 4% waste is included, how many blocks should be estimated?
An office ceiling takeoff is 11,250 sf. Ceiling tile waste is 6%. How many square feet of tile should be carried?
A framing crew averages 310 lf of partition layout and track per day. The bid includes 2,170 lf. At $1,540 per crew day, what labor amount should be carried?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
