A low mechanical proposal excludes controls wiring that appears in the specifications. What is the best bid-leveling response?

Correct Answer

A) Clarify the exclusion and carry complete controls wiring

Bid leveling requires complete comparable scope before a subcontract number is carried.

Answer Options
A
Clarify the exclusion and carry complete controls wiring
B
Carry the low number unchanged because exclusions disappear when a subcontract is signed
C
Shift the controls wiring to the permit office because inspectors price missing scope
D
Wait for the first pay application to decide whether the omitted wiring matters

Why This Is the Correct Answer

Bid leveling requires complete comparable scope before a subcontract number is carried.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.