A public bid form asks for separate prices for Alternates 1 and 2. What should the estimator do with subcontractor combined alternate pricing?

Correct Answer

C) Clarify combined pricing into separate bid-form alternates

Bid forms require prices in the requested structure so the owner can evaluate alternates.

Answer Options
A
List the combined price under both alternates because the owner can divide it later
B
Delete one alternate from the bid form if the subcontractor did not separate its quote
C
Clarify combined pricing into separate bid-form alternates
D
Use the combined alternate only in the meeting minutes after bids are opened

Why This Is the Correct Answer

Bid forms require prices in the requested structure so the owner can evaluate alternates.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.