The bid includes a $42,000 flooring allowance. The selected flooring is priced at $45,650 installed. Before markup rules are considered, what is the direct allowance overrun?

Correct Answer

A) $3,650

Compare the selected installed price with the carried allowance.

Answer Options
A
$3,650
B
$1,825
C
$42,000
D
$87,650

Why This Is the Correct Answer

Compare the selected installed price with the carried allowance.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.