A bidder discovers a math extension error after bid submission, and the instructions address corrections only before bid receipt. What is the safest preconstruction reading?

Correct Answer

B) Do not assume the bidder can revise the bid after the deadline without the stated procedure allowing it

Bid procedures control when and how modifications or withdrawals may occur.

Answer Options
A
Change the submitted bid unilaterally after opening because arithmetic mistakes are always ignored by the owner
B
Do not assume the bidder can revise the bid after the deadline without the stated procedure allowing it
C
Use the schedule of values after award to rewrite the bid number
D
Ask the subcontractor to approve the owner's bid form after opening

Why This Is the Correct Answer

Bid procedures control when and how modifications or withdrawals may occur.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.