A low electrical proposal excludes fire alarm rough-in that the other proposals include. What should the GC do before carrying the low number?

Correct Answer

A) Clarify the exclusion and level the proposals to a common scope basis

Bid leveling requires comparing proposals on equivalent scope.

Answer Options
A
Clarify the exclusion and level the proposals to a common scope basis
B
Carry the low proposal unchanged and hope the scope gap is found after award
C
Delete fire alarm rough-in from the drawings without design-team approval
D
Treat the exclusion as accepted because the proposal arrived before bid time

Why This Is the Correct Answer

Bid leveling requires comparing proposals on equivalent scope.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.