The owner issues a punch list at substantial completion. What is the GC's proper operational focus?

Correct Answer

B) Assign, track, correct, and verify punch-list items to support closeout

Closeout procedures require punch-list items to be tracked and corrected.

Answer Options
A
Treat the punch list as a new bid package unrelated to the contract and wait for separate pricing
B
Assign, track, correct, and verify punch-list items to support closeout
C
Ignore minor items until after final payment is released
D
Use the punch list to replace required permit approvals

Why This Is the Correct Answer

Closeout procedures require punch-list items to be tracked and corrected.

Was this explanation helpful?

More Contract Admin Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.